Autodesk and Vela Systems Collaborate to Provide Building Information Modeling for the Field

Using Vela Systems software --including bar-coding and radio-frequency identification (RFID) tracking technology--builders on-site can access a data-rich Autodesk Navisworks project model during the construction phase. Instead of leaving the Autodesk Navisworks model and its data behind in the office or job trailer, jobsite users can work with Vela Systems software on mobile tablet computers to access the intelligent model on-site. This makes it possible to track material production and installation, manage commissioning, conduct quality assurance/quality control inspections, do punch lists and create electronic owner-handover documentation. Autodesk Navisworks users may designate which information will be managed in Vela Systems and, as a result, the Vela Systems software enables this data to be properly managed and used in the field. The integration between the products is bi-directional and automated. The result is that the information from the field connects the "should be" state-of-design to the "as-is" state-of-construction.

New Solution Applied to Autodesk AEC Headquarters in Waltham, Mass.

During the construction of Autodesk's new AEC headquarters on Trapelo Road in Waltham, Mass., Tocci Building Corporation utilized Vela Systems Materials Tracker and Issues and Punchlists software products. By combining Vela Systems software with Autodesk Navisworks, all parties were able to monitor and track office workstations at the new Autodesk facility. Vela Systems Materials Tracker pulled objects from the Autodesk Navisworks model through an automated integration, and then captured their status information (for example, delivered, ready-to-install, installed or damaged) from the field. This field gathered data was then deposited into the Autodesk Navisworks model. Tocci and subcontractor Creative Office Pavilion were then able to visualize and monitor the installation and quality status of workstations in real-time, making it possible to plan for shortages or discrepancies accordingly.

The benefits of extending BIM to the field on the Autodesk headquarters project were threefold. First, upon delivery, the inventory of available workstations was confirmed against the model - this revealed that all necessary components were on-site ahead of the actual delivery manifests so the next phase of work could begin sooner. Then, the staging, assembly and installation processes for workstations were tracked from Vela Systems back into the Autodesk Navisworks model through color coding of model elements. This enabled the team to visualize available inventory and coordinate installation processes more efficiently. Last, the quality control processes of final inspection and owner punch lists were automated in the field with Vela Systems and linked back to the Autodesk Navisworks model, improving team communication and project delivery.

"Tying together field data with the model creates new opportunities for construction delivery methods and oversight," said Tocci Building Corporation general superintendent, Bob Tierney. "By using the integrated Autodesk and Vela Systems solution on this project, we demonstrated how we can connect the 'virtually built' building to the 'physically built' one. The model gives us better oversight because everyone can instantly visualize problem areas as 'hot spots' with live data from the field. It is the obvious next step for contractors looking to maximize the value of BIM."

"The combination of using 3D modeling tools and practicing BIM is helping to transform the building industry," said Tim Douglas, Autodesk industry solutions manager, construction. "The integration of Vela Systems Field BIM solution into Autodesk Navisworks software provides our customers with better accuracy and efficiency for the duration of the project--beginning in the design phase and continuing through field implementation and handover."

"By integrating Vela Systems and Autodesk Navisworks, our joint customers can leverage the transformative power of BIM beyond design into the construction process," said Tim Curran, CEO, Vela Systems. "By leveraging the model in the field, contractors benefit from greater efficiencies and owners get a better end product."

BIM is an integrated process that allows architects, engineers and builders to explore a project digitally before it's built. Coordinated, reliable information is used throughout the process to design innovative projects, accurately visualize appearance for better communication, and simulate real-world performance for better understanding of important characteristics such as cost, scheduling and environmental impact.

Comments (0)
Write comment
Your Contact Details:
Comment:

Perspectives

What do sensors add to a decision support system?

Written byMatt Ball
on May 22, 2012

An often-quoted Business Week article from 1999 stated that, “In the next century, planet Earth will don an electric skin…”...

Is it time for focused publications that aim to make sense of change at both the global and local scales?

Written byMatt Ball
on May 15, 2012

Change is a constant that is inevitable, but what isn't inevitable are disruptive impacts. The more we know about our...

GeoEye Proposes to Purchase DigitalGlobe

Written byMatt Ball
on May 04, 2012

The mergers and acquisitions within the geospatial technology space are white hot right now, with news Friday that GeoEye approached...

Why did Trimble buy SketchUp, and why did Google sell?

Written byMatt Ball
on April 29, 2012

It’s funny, my first reaction to the Trimble buys SketchUp news was that it was some kind of spoof, and...

If Enhanced View cuts come, why not remove resolution restrictions?

Written byMatt Ball
on April 22, 2012

A feature in the New York Times outlines the battle that is brewing in Congress to defend the use of...

Tag Cloud

Current Readers